This construction kickoff was active from July 16-26, 2020. Information on this website may no longer be current. Email us for more information.

 

The following provides an overview of construction activities. The timeline is tentative and subject to change due to weather, contractor availability or other unforeseen circumstances.

 
  • Start of construction

    August 2020
  • Erosion and sediment control measures

    August 2020
  • Installation of stormwater structures and pipe

    August-September 2020
  • Build subgrade and rock

    August-September 2020
  • Concrete and asphalt work

    September-October 2020
  • Sidewalk installation

    September-October 2020
  • Landscaping, seeding and minor patchwork

    October 2020
  • Project completion

    Oct. 30, 2020